Posted on: April 25, 2018

[ARCHIVED] 2018 PUBLIC WORKS PROJECTS

Ductile Iron Pipe - This is what is being replaced.2300 NORTH 500 WEST to 1000 W

This project is located on 2300 N between 500 W and 1000 W. It is part of a multi-phase project which when complete will provide an additional source of drinking water to the city and it will improve water pressure and flows in the area.

To provide for the safety of construction crews and the travelling public, sections of the street will be closed to thru traffic however homes within the construction area will be accessible. Interruptions in water service will happen periodically as new connections are made.

     Update: June 4, 2018……The installation of the new water line is progressing well. Once the main line is installed, then the work will begin to connect homes, fire hydrants and intersections.

Following the water line work, concrete work will begin including improvements to storm drain boxes and damaged sections of curb. All of the pedestrian curb ramps will be upgraded to current American Disabilities Act Standards.

The street will be completely repaved.


2050 N 3000 W SEWER LINE

This project is to replace the existing 2”pressure sewer pipe with a new 8”gravity flow line. New pavement will be installed after the pipe line is installed.

      Update: May 31 2018……Pipe line construction is complete.

Repaving of the street is tentatively scheduled for June 2018


630 W 1800 N to 2300 N Water Line Replacement and Street Rebuild

This project will replace the existing Water Main Line followed by reconstruction of the street including concrete repairs to curb and gutter, waterways and pedestrian ramps.

     Update: May 31 2018…….The construction of the new water main is complete with connections to intersection side streets and fire hydrants. Approximately 50 water service connections from the new main line to individual homes are scheduled to be completed over the next 2 weeks. Two crews are currently working on this but the time needed to complete the work is approximate.

Concrete work is at 50%

     Street Construction will follow the water line project. A more accurate time line for street reconstruction will be posted soon.


ROAD CLOSED TO THRU TRAFFIC or LOCAL TRAFFIC ONLY ……tells you that you NEED to take a different route and should only cross the barrier if you have no other option to reach your destination within the restricted area. For example, if the driveway to your home, worksite, a friend or relative's home can only be accessed on the restricted roadway you are LOCAL TRAFFIC and NOT THRU TRAFFIC. If your destination is outside the restricted area, you must take another route and not go THRU. These signs are in place to protect the driving public and workers at the construction site. It also helps limit dust in the neighborhood.